IJAT Vol.19 No.2 pp. 153-161
doi: 10.20965/ijat.2025.p0153
(2025)

Research Paper:

Development of Production Planning Method to Reduce Setup Time on Bending Process in High-Mix Low-Volume Production

Kazunori Yoshida*,† ORCID Icon, Hiroki Mitsuta*, Dai Kondo**, Yoshio Mitsuishi**, and Masataka Tanaka*

*Research and Development Group, Hitachi, Ltd.
292 Yoshida-cho, Totsuka-ku, Yokohama, Kanagawa 244-0817, Japan

Corresponding author

**Omika Works, Control System Platform Division, Hitachi, Ltd.
Hitachi, Japan

Received:
September 12, 2024
Accepted:
December 16, 2024
Published:
March 5, 2025
Keywords:
setup time reduction, high mix low volume production, group technology
Abstract

To realize efficient production, it is important to reduce the setup time, especially in high-mix low-volume production where the setup time is mainly spent to switch product categories. Group technology can reduce the setup time by processing parts with the same setup in the same group. However, in high-mix low-volume production, it is difficult to create large groups because there are many product categories. To address this problem, this study aims to extend group technology to create large groups with various product categories. We hypothesized that the setup conditions can be categorized into changeable and unchangeable parameters, allowing large groups to be formed by standardizing different setup parameters to the same value. Based on this hypothesis, we proposed a method consisting of four steps: creating groups using unchangeable setup parameters, ordering in a group to minimize differences in changeable setup parameters at each gap, changing changeable parameters to minimize setup time, and ordering among groups to minimize setup time. This method was validated using two sheet-metal-bending machines. Applying the proposed method reduced the setup time from 841 s to 680 s, which indicates that the proposed method is effective for setup-time reduction. To facilitate the straightforward application of this method, we will explore ways to categorize parameters as changeable or unchangeable.

Cite this article as:
K. Yoshida, H. Mitsuta, D. Kondo, Y. Mitsuishi, and M. Tanaka, “Development of Production Planning Method to Reduce Setup Time on Bending Process in High-Mix Low-Volume Production,” Int. J. Automation Technol., Vol.19 No.2, pp. 153-161, 2025.
Data files:
References
  1. [1] United Nations, “Goal 9 Department of Economic and Social Affairs.” https://sdgs.un.org/goals/goal9 [Accessed January 23, 2024]
  2. [2] A. Fysikopoulos, G. Pastras, T. Alexopoulos, and G. Chryssolouris, “On a generalized approach to manufacturing energy efficiency,” Int. J. of Advanced Manufacturing Technology, Vol.73, pp. 1437-1452, 2014. https://doi.org/10.1007/s00170-014-5818-3
  3. [3] C. Gahm, F. Denz, M. Dirr, and A. Tuma, “Energy-efficient scheduling in manufacturing companies: A review and research framework,” European J. of Operational Research, Vol.248, No.3, pp. 744-757, 2016. https://doi.org/10.1016/j.ejor.2015.07.017
  4. [4] F. A. Abdulmalek and J. Rajgopal, “Analyzing the benefits of lean manufacturing and value stream mapping via simulation: A process sector case study,” Int. J. of Production Economics, Vol.107, No.1, pp. 223-236, 2007. https://doi.org/10.1016/j.ijpe.2006.09.009
  5. [5] E. C. Eren and N. Gautam, “Efficient control for a multi-product quasi-batch process via stochastic dynamic programming,” IIE Transactions, Vol.43, No.3, pp. 192-206, 2010. https://doi.org/10.1080/0740817X.2010.521808
  6. [6] K. Fang, N. A. Uhan, F. Zhao, and J. W. Sutherland, “Flow shop scheduling with peak power consumption constraints,” Annals of Operations Research, Vol.206, pp. 115-145, 2013. https://doi.org/10.1007/s10479-012-1294-z
  7. [7] T. Gutowski, C. Murphy, D. Allen, D. Bauer, B. Bras, T. Piwonka, P. Sheng, J. Sutherland, D. Thurston, and E. Wolff, “Environmentally benign manufacturing: Observations from Japan, Europe and the United States,” J. of Cleaner Production, Vol.13, No.1, 2005. https://doi.org/10.1016/j.jclepro.2003.10.004
  8. [8] S. Shingo and N. Bodek, ”A Study of the Toyota Production System From an Industrial Engineering Viewpoint,” A. P. Dillon (Ed.), Routledge, 2019.
  9. [9] M. B. Yildirim and G. Mouzon, “Single-machine sustainable production planning to minimize total energy consumption and total completion time using a multiple objective genetic algorithm,” IEEE Trans. on Engineering Management, Vol.59, No.4, pp. 585-597, 2012. https://doi.org/10.1109/TEM.2011.2171055
  10. [10] R. Sundar, A. N. Balaji, and R. M. S. Kumar, “A review on lean manufacturing implementation techniques,” Procedia Engineering, Vol.97, pp. 1875-1885, 2014. https://doi.org/10.1016/j.proeng.2014.12.341
  11. [11] A. Allahverdi, J. N. Gupta, and T. Aldowaisan, “A review of scheduling research involving setup considerations,” Omega, Vol.27, No.2, pp. 219-239, 1999. https://doi.org/10.1016/S0305-0483(98)00042-5
  12. [12] M. M. Liaee and H. Emmons, “Scheduling families of jobs with setup times,” Int. J. of Production Economics, Vol.51, No.3, pp. 165-176, 1997.
  13. [13] S. S. Heragu, “Group Technology and Cellular Manufacturing,” IEEE Trans. on Systems, Man and Cybernetics, Vol.24, No.2, pp. 203-215, 1994. https://doi.org/10.1109/21.281420
  14. [14] S. K. Gupta and D. A. Bourne, “Sheet metal bending: Generating shared setups,” J. of Manufacturing Science and Engineering, Trans. of the ASME, Vol.121, No.4, pp. 689-694, 1999. https://doi.org/10.1115/1.2833107
  15. [15] L. R. Abreu, J. O. Cunha, B. A. Prata, and J. M. Framinan, “A genetic algorithm for scheduling open shops with sequence-dependent setup times,” Computers and Operations Research, Vol.113, Article No.104793, 2020. https://doi.org/10.1016/j.cor.2019.104793
  16. [16] M. H. R. Utiyama, M. G. Filho, and P. C. Oprime, “An alternative for improving setup times and time between failures aiming at manufacturing lead time reduction,” Production Engineering, Vol.15, pp. 651-665, 2021. https://doi.org/10.1007/s11740-021-01048-0
  17. [17] S. Shingo, “A Revolution in Manufacturing: The SMED System,” Routledge, 1985.
  18. [18] S. C. Trovinger and R. E. Bohn, “Setup Time Reduction for Electronics Assembly: Combining Simple (SMED) and IT-Based Methods,” Production and Operations Management, Vol.14, No.2, pp. 205-217, 2009. https://doi.org/10.1111/j.1937-5956.2005.tb00019.x
  19. [19] B. Das, U. Venkatadri, and P. Pandey, “Applying lean manufacturing system to improving productivity of airconditioning coil manufacturing,” Int. J. of Advanced Manufacturing Technology, Vol.71, pp. 307-323, 2014. https://doi.org/10.1007/s00170-013-5407-x
  20. [20] S. S. Wang, C. C. Chiou, and H. T. Luong, “Application of SMED Methodology and Scheduling in High-Mix Low Volume Production Model to Reduce Setup Time: A Case of S Company,” IOP Conf. Series: Materials Science and Engineering, Vol.598, Article No.012058, 2019. http://dx.doi.org/10.1088/1757-899X/598/1/012058
  21. [21] AMADA Co., Ltd. “Bending Tools Tooling Products.” https://www.ai-link.ne.jp/kanademo/Public_sptoolnavi/products/index.html 2020. [Accessed November 15, 2024]

*This site is desgined based on HTML5 and CSS3 for modern browsers, e.g. Chrome, Firefox, Safari, Edge, Opera.

Last updated on Mar. 04, 2025